17/11/08 - Site clean out side and cleaners going well inside..
15/11/08 - Plumbers were in today (Sat) and yesterday...
14/11/08 - Guess it takes a while to put in 60 downlights....
13/11/08 - Sparkies again...
12/11/08 - Sparkies are in today, so we can see and the tilers have finished...
11/11/08 - Tilers won't leave us alone...
10/11/08 - Tilers are back again...
8/11/08 - Tilers in on a weekend... woo hooo
7/11/08 - Tilers still going
6/11/08 - Tilers on board
5/11/08 - Painters have now moved outside and the tilers have made an apperance
4/11/08 - More Painting
3/11/08 - Painters still painting
31/10/08 - Painters still painting
30/10/08 - Painter in again.. Doing window frames..
29/10/08 - Plumbers in connecting downpipes...No painters
28/10/08 - No Painters but rendering started...
27/10/08 - Finally painting started..
24/10/08 - No one worked again....
23/10/08 - Brickies and chippies in today
22/10/08 - It's Wednesday... Of course they didn't work...
21/10/08 - Chippies in for a couple of hours
20/10/08 - No work again... Pissing me off...
17/10/08 - No work today
16/10/08 - Chippies in. Change windows
15/10/08 - It's Wednesday silly... No Work..
14/10/08 - Renderers have been in to frame up..
13/10/08 - We have downpipes...
10/10/08 - As below...
09/10/08 - Roof Tilers in for ridge works
08/10/08 - Gas Supply connected
07/10/08 - Cabinet makers back in
06/10/08 - No Work
03/10/08 - Plumbers back in to relocate the bathtub and taps
02/10/08 - Chippies finishing up today, alfresco & frett work
01/10/08 - No work done today
30/09/08 - Brick washing completed
29/09/08 - No work done
26/09/08 - Chippies still working, eaves, fret work & Alfresco.
25/09/08 - Chippies are back again, shelving, more eaves, fret work and alfresco work going on..
24/09/08 - No one there today....No work...
23/09/08 - Chippies still going strong...
22/09/08 - Chippies again.....
21/09/08 - It's a Sunday!!!! Chippies still working...
20/09/08 - It's a Saturday!!!! Chippies still hanging doors....
19/08/08 - Plasterers and chippies going on..Wood fret work and finials delivered....
18/09/08 - Plasterers doing up cornices, internals doors delivered..
17/09/08 - Cabinet makers still going strong..
16/09/08 - No plasterers, no brickies, but we have cabinet makers....
15/09/08 - Only one plasterer there today, apparently cornicees will be tommorrow... No brickies there though... I know who has them...lol..
12/09/08 - More plastering, only one guy this morning, Brickies are still there though..
11/09/08 - Still plastering, back to 4 guys..But we have the brickies back...lol
10/09/08 - Still plastering, now 5 guys...5 Roof tilers also rocked up for morning smoko and did nothing..
09/09/08 - More plastering...
08/09/08 - Plasterers are there today. 4 of them...and the garage supports came down...
05/09/08 - No Brickies today..
04/09/08 - Brickies have now done 4 days in a row for two weeks running now... I am impressed...Insulation completed, I was told the plasterers should be here next week...
03/09/08 - Brickies are back again...3 days in a row...
02/09/08 - Brickies came back again..Insulation started going in...
01/09/08 - Brickies are back...
29/08/08 - Mozzed myself..... The best day of the week, & where are the brickies??? Not at our building site anyway..But the insulation bats arrived...
28/08/08 - Brickies are still going, surely they can't keep this pace up???
27/08/08 - Solar panels were installed today and the brickies are back..
26/08/08 - This is getting rediculous, the brickies are back on site again!!!!
25/08/08 - Christ, four days in a row!!!
22/08/08 - Jesus, brickies are running for a hat trick!!!! Also the ensuite window has been moved.
21/08/08 - Brickies two days running!!! Chippies are in also to prop up the garage.
20/08/08 - Brickies finally back.
19/08/08 - Nothing done again....
18/08/08 - Nothing done
11-15/08/08 -Bloody rained for the most part.
14/08/08 - Hole dug out for bath tub.
11/08/08 - Pre plaster inspection completed. Score 98%
08/08/08 - Brickies started work today...
07/08/08 - Our Dodgy lock up door arrived today and brickies mixer dropped off.
06/08/08 - Nothing Happened
05/08/08 - Nothing Happened..
04/08/08 - Roof tilers have finsished for the time being. They will be back later in the build to morter them in place.
01/08/08 - Well the bricks have arrived..
31/07/08 - Still battening and the tiles have arrived...
30/07/08 - Roof guys were there today battening down the hatches in prep for the tiles..
28/07/08 - Nothing was done by the chipies or anyone.
25/07/08 - Chippies up there today, I don't know what they were doing as yet I will find out more tomorrow.On another note our SS has left and our new one is the owner...cool..I hope he worries about our house as much as he does about his business..lol..
24/07/08 - We are wrapped.... Sarking completed.
20/07/08 - Ducted vacuum pipes being installed.
18/07/08 - Guttering, Facia's and Windows and doors installed
16/07/08 - Plumbing and Gas fitting started and completed today, Yippee...
15/07/08 - All trusses on house and garage completed.
14/07/08 - Garage frame work started
09/07/08 - Windows, Door Frame & Sliding Doors Delivered Today
08/07/08 - Trusses Delivered
01/07/08 - Frame Woks Started Today
16/06/08 - Slab poured today.
13/06/08 - Today it pissed down with rain all bloody day. So no slab today... Bugger...
12/06/08 - Slab framers completing their thing.
11/06/08 - Slab framers doing their thing.
04/06/08 - Plumbers finished their plumbing.
03/06/08 - Plumbers are in the ground, doing there thing. Danny our fencing guy started and completed his job for the left and partial rear fencing of the property.
29/05/08 - Piers have now been completed.
28/05/08 - Back to the tilers
27/05/08 - Onsite port-a-loo landed.
26/05/08 - Piers are dug and some pouring.
21/05/08 - Power box installed won't be connected untill slab is layed. Also had to go back to the tilers, didn't like our initial selections.
13/05/08 - Water meter installed x 2. 1. For normal water. 2. Is for the recycled water, otherwise known as the third pipe or purple pipe.
12/05/08 - Interim Approval for plumbing from Sth East Water
Vanessa is my wife of 4 years, Nicholas is our son he was born 26/08/06 and Bailey is our Golden Retriever he is 4 and can't wait 'til Nicholas is old enough to play with him.
The name Arkraider was taken from MY first dog, a Golden Retriever (surprsie), his name was Ribbonwood Arkraider. He was a show dog and named after a battle cruiser from the 2nd World War.
No comments:
Post a Comment